Extension of works on Beverley Street, Wentworth

December 1, 2023 8:33 am in by

Sewer works commenced Monday 13 November 2023, with an original completion time of 5:00pm on Friday 1 December 2023 (approximately 3 weeks).

Due to wet weather, the works require an extension of seven (7) days.

Traffic control is in place during the works:

Article continues after this ad
Advertisement
  • Beverley Street (between Adelaide Street and Murray Lane) is closed to cross traffic
  • Murray Lane (between Beverley Street and Short Street) will have access for local traffic only, with the Beverley Street end of Murray Lane being closed.

Both Murray House and Bysouths Garage remain accessible, with parking required on Murray Street.