July 10, 2026 6:37 am in by

Motorists are advised that River Road, between the Silver City Highway and Link Road in Buronga, will re-open on Monday 13 July.

A temporary reduced speed limit will be in effect upon opening.

Motorists are urged to drive to the conditions and observe all signposted speed limits.

Article continues after this ad
Advertisement

The reopening follows a five-week closure to complete sealed road pavement rehabilitation and widening works along a 2.92km section of the road.

The upgrade delivers a new 7.4-metre sealed width.

These works were funded by the Regional Emergency Road Repair Fund (RERRF).

Wentworth Shire Council has thanked the community and road users for their continued patience and cooperation during this essential infrastructure upgrade.