Trafficcone

Construction of Barclay Square, Red Cliffs
Start: 7 am, Monday 5 August 2019
Finish: 5 pm, Friday 4 October 2019

Shared Path Construction
Eleventh Street between Cowra Avenue and Belar Avenue, Irymple
Start: Early July 2019
Finish: Late October 2019

Installation of Pedestrian Islands and 40km/ hour signage
Area 4 - Black Pl (Benetook Ave intersection), Eastside Dve (Ellswood Cres and Cureton Ave intersections), Wirrayway Dve (Ellswood Cres intersection), Mildura
Start: Mid July 2019
Finish: Early August 2019
Area 7 - Chardonnay Dve (Fourteenth St intersection), Lisa Crt (Etiwanda Ave intersection), Hornsey Pk (Etiwanda Ave intersection), Barry Ave (Eleventh St intersection), Mildura
Start: Early July 2019
Finish: Early August 2019
Area 16 - Orange Ave (Eleventh St intersection), Lemon Ave (Eighth St, Ninth St, Tenth St and Eleventh St intersections), Magnolia Ave (Eighth St, Ninth St, Tenth St and Eleventh St intersections) Mildura
Start: Mid July 2019
Finish: Mid August 2019
Area 17 - Pearl Ave (Eleventh St, Tenth St and Ninth St intersections), Victor Ave (Tenth St and Ninth St intersections), Almond Ave (Eleventh St and Tenth St intersections), Ruby Ave (Eighth St and Seventh St intersections) and Mabel Ave (Eighth St and Seventh St intersections), Mildura
Start: Mid July 2019
Finish: Mid August 2019

Also, some work to commence shortly on Deakin Avenue and 17th Street and The Abbotsford Bridge at Curlwaa/Yelta is to receive some work in the coming days.