Header Weekend with Dave

Road-under-construction

Road Repair
Sixteenth Street between Karadoc Avenue and Sandilong Avenue, Irymple
Traffic management / reduced speed
Start: 7am, Tuesday 28 May 2019
Finish: 5pm, Friday 26 July 2019

Road Reconstruction
Walnut Avenue between Sturt Highway and Nineteenth Street, Mildura
Start: 7.30am, Monday 1 July 2019
Finish: 5pm, Friday 26 July 2019

Shared Path Construction
Eleventh Street between Cowra Avenue and Belar Avenue, Irymple
Start: Early July 2019
Finish: Late October 2019

Installation of Pedestrian Islands and 40km/ hour signage
Area 6 - Dennis Ave, Euneva Dr, Christie Pde, Brian St, Keam St, Hazeldene St, Avocado St, Eaglesham St, Beech Ave, Brentwood Ave, Baylee Ave, Windsor St, Giddings Pl, Weir Cres, Mildura
Start: Late May 2019
Finish: Late July 2019
Area 19 - Toorak Ave (Eleventh St and Twelfth St intersections), Cameron Ave (Eleventh St and Twelfth St intersections), Desroy Ave (Eleventh St and Twelfth St intersections), Jenkins Pl (Eighth St and Ninth St intersections), Cherry Ave (Eighth St and Ninth St intersections), Seventh St (Chaffey Ave intersection), Mildura
Start: Mid May 2019
Finish: Late July 2019
Area 17 - Pearl Ave (Eleventh St, Tenth St and Ninth St intersections), Victor Ave (Tenth St and Ninth St intersections), Almond Ave (Eleventh St and Tenth St intersections), Ruby Ave (Eighth St and Seventh St intersections) and Mabel Ave (Eighth St and Seventh St intersections), Mildura
Start: Mid July 2019
Finish: Mid August 2019